Full Planning Permission Awarded

The District Assembly has awarded full planning authority to the Formena site, keeping things on track for this, our second hospital site.

Hospital Approach Road Completed

Our close working relationship with the District Assembly has stood us in good stead to get underway with site development at Fomena. Using NMSI designs, the DA engineers have completed the approach road to the hospital site, including a well constructed colvert. The DA chief executive is standing by, ready to assist in the first steps of site development, vegetation and soil clearance. The DA is very happy to be involved in the first steps of development of their hospital

Assessments and Investigations

The geological site investigation has been completed, revealing the good news that no rock has been encountered and there is good engineering soil throughout the Fomena site. Additionally the Environmental and Social Impact Assessment scoping study has been completed and submitted to the EPA licencing authority.