Abetifi NMSI Team on site to assess tree retention and replanting at Abetifi During the Abetifi site clearance work and vegetation strip, an NMSI team is on site…adminnmsiJanuary 15, 2015
AbetifiProgress Site Mobilisation and Clearance is underway at Abetifi Site mobilisation and clearance work has begun at Abetifi. With boundaries defined and the hard…adminnmsiJanuary 12, 2015
Giving BackProgress Christmas Appeal for Noyaa In our ongoing commitment to supporting Jamestown community education charity Noyaa, we are appealing for…adminnmsiDecember 18, 2014
KumawuProgress Kumuwa Hospital Site – Beginning of Major Earthworks Now that the site vegetation and topsoil has all been cleared, work has begun on…adminnmsiDecember 17, 2014
FomenaProgress Fomena District Hospital Site Progress Significant progress has been made on the Fomena District Hospital Site. The site's major earthworks…adminnmsiDecember 17, 2014
DodowaProgress Steelwork going up on Dodowa Hospital Wards Progress on the Dodowa District Hospital Site is going well. Steelwork can now be seen…adminnmsiDecember 17, 2014
DodowaProgress Dodowa hospital site now visible on Google Earth Google Earth's satellite has recently passed over the Dodowa District Hospital Site and the layout…adminnmsiDecember 9, 2014
Uncategorized Fomena Site Mobilisation Complete With new permanent on-site manager and engineer along with the rest of the team, this…adminnmsiDecember 2, 2014
DodowaProgress Dodowa Main Clinical Building: Steel 95% complete Steel on the main clinical building at Dodowa is nearly finished, with 95% of it…adminnmsiNovember 27, 2014
DodowaProgress On Site Staff As work rolls out on multiple sites, the project is able to fulfil commitment to…adminnmsiNovember 14, 2014